The Generate Item Lead Time job runs through all items and generates a Default Lead Time and a Estimated Lead Time with each lot size from the Lead Time Setup.
If the Calculate Low-level Codes field is activated in the setup, the function Calculate Low-level Code is executed before the Leadtime calculation is done.
The working date is used for the valid surcharges, unless the execution time is later than the time stored in the setup, in which case the following day is used.
When the Item Lead Time is generated, the Make-To-Stock Lead Time field from the Lead Time per Item table is also calculated based on the Make-To-Stock Work Center Group Code.
Additionaly the fields Default Lead Time Routing ,Default Max Lead Time Component and Estimated Max. Lead Time Component were calculated without Capacity Surcharges.
The field Estimated Lead Time Routing will be calculated with Capacity Surcharges.
The job can be executed periodically using the job queue.
For more information, see Working with the App.